How Two Purification Concepts Are Being Tested Side by Side at Yara

How Two Purification Concepts Are Being Tested Side by Side at Yara

New step in industrial water treatment

Removing high nitrogen concentrations from water that contains hardly any phosphorus or carbon? That’s not your average treatment challenge. At Yara International’s production facility in Sluiskil, where some 5 million tons of nitrogen-based fertilizers and industrial chemicals are produced annually, precisely such challenging water streams arise. Limiting discharges, using water more intelligently, and at the same time being prepared for stricter regulations: it was all on the table. That’s why Yara chose Rietland, a partner that doesn’t see natural purification as old-fashioned, but as a strong technical foundation for the future.

The pilot plant, realized in the spring of 2026, consists of two large basins, each measuring 18 m × 5 m × 2 m. With a filter volume of 180 m³ per basin—360 m³ in total—there is ample space for biological processes. The basins are filled with expanded clay pellets, Argex. Here, bacteria do the heavy lifting. The goal? Transform nitrogen via nitrification and denitrification. Because the water stream contains little carbon, extra carbon is dosed to support the denitrifying bacteria.

The pilot at Yara consists of 2 basins of 18m x 5m in which high nitrogen concentrations are removed.
The pilot at Yara consists of 2 basins of 18m x 5m in which high nitrogen concentrations are removed.

Innovation: FBA® and Fill & Drain tested side by side

In Sluiskil, two concepts are tested side by side. One system operates with Forced Bed Aeration, FBA®, where active aeration creates oxygen-rich zones for nitrification. The second, non-aerated basin provides for denitrification. The other concept is Fill & Drain. By cyclically raising and lowering the water level in the Fill & Drain system, oxygen is passively drawn in and then oxygen-poor conditions are created for denitrification. These two systems can be tested in the same pilot. Currently, the operation of the flow-through filters with aeration is being tested. In the second year, the Fill & Drain will be tested.

The pilot plant is deliberately designed so that different settings for aeration intensity and cycle duration can be tested without major modifications to the infrastructure. Not only are the removal efficiencies of nitrogen and phosphorus compounds monitored, but also operational reliability and maintenance needs. Dynamically controlling process conditions—such as by varying FBA aeration based on online oxygen and nitrate measurements, or by adjusting the Fill & Drain cycles to fluctuating influent loads—should show to what extent the system ‘adapts’ to the plant’s daily practice.

This project opens the door to applications in sectors where classic treatment does not easily fit. Curious how this large-scale pilot removes nitrogen-rich water streams?

Read More Here
Testimonials

Testimonials

What our customers say Testimonials Ghent University To drastically reduce the use of city and groundwater, Tech Lane Ghent opted for ...

blogs

In the spotlight

In our blogs, we share insights, developments, and practical knowledge about water treatment and circular water use.

contact

How can we help you?

Do you have questions about any of our products or services? Feel free to contact us!